Current condition on “Sunrise’s” construction site:

16 December 2017 Year

Foundation is filled with concrete;
The walls of underground parking are totally filled;
There are filled elevators shafts, underground space’s columns and diaphragms;
The underground parking’s tile is poured;
There are filled first floor’s diaphragms, columns and elevator-shafts;
The firs floor’s tile is poured also;
There are filled second floor’s diaphragms, columns and elevator-shafts, staircases also;
At the moment there are preparatory works for pouring tile of second floor.